Context
Brigil, a real estate developer in the Ottawa–Gatineau region, set out to transform the city’s oldest shopping centre into Canevas: a mixed-use neighbourhood with residential units, green space, a public square and gathering places. My part was the commercial side: redeveloping the existing 100,000 sq. ft. commercial centre, Espace Canevas, into a commercial and community destination.
The project had many moving parts: a fixed budget approved by the CFO and board; contractors, architects and engineers; municipal permits; and existing tenants who had to keep operating through construction.
The hard part: transforming the centre while existing tenants kept operating, inside a fixed budget approved by the CFO and board, and a 16-month window.


Photos: Brigil, from brigil.com/canevas.
Objective
Deliver the redevelopment on budget and on schedule, keep existing tenants whole during construction, and then fill and activate the space so it generated recurring revenue.
My responsibilities
Jessy Desjardins, Brigil’s Vice President of Development and Design, hired me on the strength of what I had built at Ke Ola. He saw that ownership as the right fit to help start the Canevas project with him.
As Commercial Coordinator (2021–2022), on a two-person team with Jessy Desjardins for a $1.8M, 16-month redevelopment. Jessy made the decisions; I ran the coordination end to end:
- Budget and cost control: built the project budget and tracked it against actual construction costs.
- Schedule management: tracked the schedule, milestones and deliverables across contractors and consultants.
- Approvals and reporting: presented the budget for approval to the CFO and, when needed, the board; reported progress and explained anything that went off track.
- Design and permits: coordinated the plans, 3D renderings and municipal permits.
- Procurement: sourced contractors and coordinated contract awards.
- Stakeholder management: coordinated architects, engineers, city officials (municipal permits) and existing tenants during the works.
- Risk and issue management: tracked open issues and worked with specialists to resolve them before they hit the schedule.
As Commercial Development Manager (2022–2023), a promotion once the renovation was complete:
- Commercial negotiation: negotiated 15+ commercial leases, from proposal through execution, for $50K+ in recurring monthly revenue.
- Partnerships and tenant relationships: managed tenant relationships, operational requests and local partnerships.
- CAPEX/OPEX: tracked capital and operating expenses for the site.
- Programming and activation: created annual event programming with tenants and local partners to bring visitors to the site.
I also coordinated event communications, including the Espace Canevas Instagram launch.
Related coursework, taken since: Foundations of project management · Advanced project planning · Project execution, monitoring and control · Corporate financial management.
Strategy & execution
One source of truth for budget and schedule
I kept the budget, schedule and open-issues list current so leadership could make approval decisions quickly and with the same numbers in front of everyone.
Coordinating many stakeholders
Contractors, consultants, the city and tenants each had different priorities and timelines. My job was to keep the dependencies between them visible and to escalate early when something threatened the schedule.
From construction to activation
A renovated building doesn't fill itself. Once the works wrapped up, I moved into leasing and community programming — launch events, terrace activations and live music with tenants and partners — to build foot traffic and make the space desirable for new tenants.
Evidence






Results
Lessons learned
- One source of truth speeds up decisions. Approvals with the CFO and board moved faster when everyone looked at the same budget and schedule.
- A building is only as good as its activation. Construction ended the project plan, not the work: leasing and events are what turned the space into revenue.
- What I would do differently now. With what I have since learned in project execution, monitoring and control, I would track performance with earned value (CPI and SPI) rather than budget against actuals alone, to see schedule and cost drift earlier.
Learn more: espacecanevas.com ↗ · brigil.com/canevas ↗